Construction Update - Week of March 11, 2013

Work continues both at the exterior and interior of the building. As the canopy framing and sheathing continue, the waterproofer is close behind, sealing these roof elements in preparation of metal panels.
Framing, sheathing and waterproofing at roof elements
 
The roofers are continue with the TPO membrane installation at the main roof; once complete they will focus their efforts on the vestibule roof.
 
TPO membrane installed around mechanical equipment
 
The glazers continue to install storefront and curtainwall frames  
 
 
 
 
 
 