Monday, February 4, 2013

Construction Update - Week of February 4, 2013

Precast is in its final week of erection, as the south, east and west elevations are all nearing completion. The glazers continue to field measure openings to receive aluminum frames. The north elevation curtainwall will be ready for glass early next week. Framing and blocking continues at the roof parapet and vestibule roof line. As soon as the roof element frame is in place on the south and east elevations, sheathing and waterproofing will commence with TPO roofing membrane installation to follow.

View of the building from Topeka looking south
 
 
NW corner of the building: vestibule and roof canopy framing


SE corner of the building: precast near complete at south and east elevations