Work continues to progress onsite as the building starts to really take shape. About 30 pieces of precast remain to be set on the South, East and West elevations. Glazing installation commenced on the north elevation this week as the glazers took field measurements, welded clips, and started installing the storefront aluminum framing. Carpenters have been laying track and framing walls on the 2nd floor as well as framing for the roof features at the SE corner and on the north end of the building.
Precast column covers and spandrel panels at the SE corner of the building
View of the building from the NE corner of Douglas and Topeka
Precast panels sitting on truck beds awaiting erection
Interior framing at level 2 seen beyond
Framing commencing at the roof line