Activity onsite continues at a feverish pace. The exterior glass systems are near 100%, with only the vestibule remaining. The TPO membrane installation is complete at the building and vestibule, the roofers will be back in a couple weeks to complete the required metal flashing.
North elevation - curtainwall complete
South and East Elevations
SE curtainwall complete - canopy framing ready for metal panels
East Elevation
Most of the activity has now turned to the interior. Metal stud framing at the interior and exterior walls are complete on 2nd floor and near complete on 1st floor. Framing is well underway at the soffits and hard-lid ceilings. Drywall and taping has commenced on 2nd floor, painters to start in the next few weeks.
Framing at the 'coned' ceiling within the Town Hall
Installed projector and screens at east side of Town Hall
Vanity frame at 1st floor restroom
Grand Stair - concrete placed, temp railing, soffit framing
Open stairs from 2nd floor to 3rd floor
Corridor at South end of building - window sill installation
2nd floor conference room - ready for glass installation
Open atrium, looking west from one of the Classrooms