Structural steel erection has commenced! With foundation work complete last week, the 60 ton crane was mobilized and set-up onsite Friday. The first column was set Monday afternoon, NW of grid line E-1 at the corner of the new vestibule link. The steel erection duration will be 5 weeks, with metal decking to start after 3 weeks.
60-ton crane set-up within building pad
Steel progress - Monday 10/22
There is roughly 210 tons of structural steel material on this project. The largest steel member is a W24 x 68 beam at the SE corner of the building
Structural steel staging onsite
Steel progress - Tuesday 10/23
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.