Thursday, October 25, 2012

Construction Update - Week of October 22

Structural steel erection has commenced! With foundation work complete last week, the 60 ton crane was mobilized and set-up onsite Friday. The first column was set Monday afternoon, NW of grid line E-1 at the corner of the new vestibule link. The steel erection duration will be 5 weeks, with metal decking to start after 3 weeks.

60-ton crane set-up within building pad

 Steel progress - Monday 10/22
 
There is roughly 210 tons of structural steel material on this project. The largest steel member is a W24 x 68 beam at the SE corner of the building

Structural steel staging onsite
 
 
Steel progress - Tuesday 10/23
 
 